So, Kory hasn't been seen or heard from since I talked with Amy on January 21st.
We've talked with Dulce several times and each time, she has said that forming for the deck and pouring of the deck is about to happen. Well, the deck people were here today and we took time off of work to make sure everything was going as planned. It's a good thing we did that.
Turns out that some of the plumbing for the pool was in the way of the deck. The plumbers came over and cut the pipes and left. Now, plumbing repairs need to be made. And, the fill dirt had been put up close to the house instead of in the ramada where it is needed. And, there wasn't enough fill dirt in the yard. Of course, the masons already put up the exterior block wall, so the deck guys are using a tiny, little tractor to move little piles of dirt into the yard.
And, Shane and I found out that the electrical for the lighting in the stairs has not been run. Nor has the sleeve for the plumbing to the planters. The masons had told us that the deck guys would do this and the deck guys said that they weren't responsible for it. The deck supervisor called Kory and he said he'd take care of it tomorrow. He'd better, because the deck is supposedly being poured on Friday no matter what.
In addition, there are chipped tiles and crumbling or non-existant grout around the edges of the pool.
Who knows what will happen next???